IMPLEMENTATION SCHEDULE 2002
week of Feb 18, Order system hardware.
week of Mar 4, Project Manager site visit. DRA Policy File changes cease.
March 7, Videoconference, Unicorn policy files overview.
week of Mar 25, WYLD Staff training.
Apr 5, WYLD Network Meeting.
week of Apr 8, System administration training in Huntsville for WYLD staff.
week of May 6, Confirmation of site readiness for completion of installation.
week of May 20, Test and production servers received and installed.
May 24, (Friday) Cease cataloging on WYLD system at end of business. Note, this item updated 5/3/02
week of May 27, Review and use data on test server. WYLD Staff training.
week of June 3, Policy changes made to test and production servers.
week of Jun 10, Full extracts of data loaded on production server and prepped.
week of Jun 17, New full extract of users and circ records loaded on production server.
Wednesday, June 19, 9:00pm - Cease circulation on DRA system and go on standalone SIRSI client.
week of Jun 24, "Go Live" consultant on site. Final load of circ and users data. Load standalone transactions. Review data and prepare for "go live" date.
July 1, Go live on SIRSI Unicorn.